02 Jul 2017
(MENAFN) Phase one of the Airport Road expansion project will be finished by the end of this year with the whole redeveloped freeway to open for traffic by mid next year.
Additionally, work on the Dh404mn project involves building of many multi-level intersections, with almost half of the work on most intersections finished.
Accordingly, 50 percent work on the development of Al Rashidyia-Casablanca Road intersections has been finished.
Meanwhile, the progress in building work has reached 70 percent in the flyover at Nad Al Hamar intersection, while completion rate in the flyover at Casablanca intersection reached 50 percent.
MENAFN0207201700450000ID1095590551
MENAFN0207201700450000ID1095590551
01 Mar 2026
BBK activates partial remote working system for its workforce to ensure employee and customer safety and service continuity
24 Feb 2026
BBK discloses its financial results for the year ended 31st December 2025
05 Feb 2026
BBK announces December Al Hayrat Grand Prize winners and another wave of Grand prizes for February
26 Jan 2026
BBK Enhances Autumn Fair 2026 Experience with Customized Rewards and Premium Services
This website uses cookies to ensure you get the best experience and by clicking “I Accept” below, you consent to the use of cookies. Learn more