10 Aug 2017
(MENAFN) Nakheel, the developer of Dubai’s palm islands, has given USD117mn of deals on its Diera Islands development.
Meanwhile, the orders comprise the building of a sewage treatment plant, a district cooling plant, a substation and piling work for an 800-room resort.
Accordingly, the developer has now invested almost 7.5bn dirhams in infrastructure and construction contracts for Deira Islands.
In April, the developer awarded a construction contract worth 4.2bn dirhams for Deira Mall, which will become the centerpiece attraction of the development.
MENAFN1008201700450000ID1095714587
MENAFN1008201700450000ID1095714587
17 Sep 2025
BBK and CrediMax launch exclusive offers for customers in collaboration with The Ritz-Carlton, Bahrain
31 Aug 2025
BBK announces an exceptional 6-month grace period financing campaign for Personal and Car Finance customers
13 Aug 2025
BBK’s BD 5,000,000 Al Hayrat scheme awards BD 680,000 to 390 Al Hayrat winners in August and September
04 Aug 2025
HM the King’s Support for Youth is an Inspirational Model for Their Empowerment Journey
28 Jul 2025
BBK discloses its financial results for the half year ended 30th June 2025
20 Jul 2025
CBB approves the transfer of the retail banking operations of HSBC Bank Middle East, Bahrain Branch to BBK
This website uses cookies to ensure you get the best experience and by clicking “I Accept” below, you consent to the use of cookies. Learn more