(MENAFN) The Oman Elect Transmission Co. (OETC) aims to invest USD 776.65mn over a three-year period for building new transmission lines for evacuating power.
Accordingly, half of this amount will be invested in helping evacuation of power from the power plant coming up at Sohar (Sohar 3) and Ibri.
Moreover, a group led by Mitsui signed a deal earlier this year to build two independent gas-fired combined cycle power plants with 3,150 capacities.
In addition, the firm had raised USD 1bn from overseas markets in 2015 for funding investment programs.
17 Sep 2025
BBK and CrediMax launch exclusive offers for customers in collaboration with The Ritz-Carlton, Bahrain
31 Aug 2025
BBK announces an exceptional 6-month grace period financing campaign for Personal and Car Finance customers
13 Aug 2025
BBK’s BD 5,000,000 Al Hayrat scheme awards BD 680,000 to 390 Al Hayrat winners in August and September
04 Aug 2025
HM the King’s Support for Youth is an Inspirational Model for Their Empowerment Journey
28 Jul 2025
BBK discloses its financial results for the half year ended 30th June 2025
20 Jul 2025
CBB approves the transfer of the retail banking operations of HSBC Bank Middle East, Bahrain Branch to BBK
This website uses cookies to ensure you get the best experience and by clicking “I Accept” below, you consent to the use of cookies. Learn more