10 Jul 2017
(MENAFN) A Mitsui & Co Ltd-led consortium achieved progress in building two main natural gas-fired power projects in Oman, which will have a joined capacity of 3.219MW.
Moreover, the Ibri Independent Power Project will get power of 940MW from April 2018, with the whole 1.509MW generation projected from April 2019.
Meanwhile, Sohar 3 is scheduled to receive full capacity of 1.710MW from Jan 2019, while the cooling tower work is progressing at the Sohar project.
In addition, the Mitsui-led group has tight deadlines to finish these two projects as OPWP is aiming to generate power amid two years.
MENAFN1007201700450000ID1095611036
MENAFN1007201700450000ID1095611036
17 Sep 2025
BBK and CrediMax launch exclusive offers for customers in collaboration with The Ritz-Carlton, Bahrain
31 Aug 2025
BBK announces an exceptional 6-month grace period financing campaign for Personal and Car Finance customers
13 Aug 2025
BBK’s BD 5,000,000 Al Hayrat scheme awards BD 680,000 to 390 Al Hayrat winners in August and September
04 Aug 2025
HM the King’s Support for Youth is an Inspirational Model for Their Empowerment Journey
28 Jul 2025
BBK discloses its financial results for the half year ended 30th June 2025
20 Jul 2025
CBB approves the transfer of the retail banking operations of HSBC Bank Middle East, Bahrain Branch to BBK
This website uses cookies to ensure you get the best experience and by clicking “I Accept” below, you consent to the use of cookies. Learn more