10 Jul 2017
(MENAFN) A Mitsui & Co Ltd-led consortium achieved progress in building two main natural gas-fired power projects in Oman, which will have a joined capacity of 3.219MW.
Moreover, the Ibri Independent Power Project will get power of 940MW from April 2018, with the whole 1.509MW generation projected from April 2019.
Meanwhile, Sohar 3 is scheduled to receive full capacity of 1.710MW from Jan 2019, while the cooling tower work is progressing at the Sohar project.
In addition, the Mitsui-led group has tight deadlines to finish these two projects as OPWP is aiming to generate power amid two years.
MENAFN1007201700450000ID1095611036
MENAFN1007201700450000ID1095611036
01 Mar 2026
BBK activates partial remote working system for its workforce to ensure employee and customer safety and service continuity
24 Feb 2026
BBK discloses its financial results for the year ended 31st December 2025
05 Feb 2026
BBK announces December Al Hayrat Grand Prize winners and another wave of Grand prizes for February
26 Jan 2026
BBK Enhances Autumn Fair 2026 Experience with Customized Rewards and Premium Services
This website uses cookies to ensure you get the best experience and by clicking “I Accept” below, you consent to the use of cookies. Learn more