(MENAFN) Saudi Elect Co. (SEC) proclaimed that it has finished installation and operation of a number of elect transmission and interconnection projects at a total cost of SR5.5bn.
Moreover, they involve six plants for transmitting elect energy, five aerial lines for elect interconnection between a number of northern cities and areas.
Accordingly, the electric projects operated currently are one of the largest projects in the northern regions of the kingdom and will contribute to linking the northern areas with the main grid.
Additionally, the projects awarded in April and May of 2014 involved construction of six main plants, namely Waad Al Shamal Plant, Al Qurayyat Plant, Al-Jouf Plant 2 and others.
MENAFN3105201700450000ID1095524135
MENAFN3105201700450000ID1095524135
28 Jul 2025
BBK discloses its financial results for the half year ended 30th June 2025
20 Jul 2025
CBB approves the transfer of the retail banking operations of HSBC Bank Middle East, Bahrain Branch to BBK
08 Jul 2025
BBK proudly launches the third edition of “Grow” and welcomes 20 Bahraini graduates
03 Jul 2025
BBK hosts executive leadership session on digital assets in collaboration with Rain
02 Jul 2025
BBK launches the largest-ever Al Hayrat Prizes, offering BD 5 million to over 2,000 winners
16 Jun 2025
BBK and CrediMax Offer Exclusive 20% Discount on Turkish Airlines Flights for Cardholders
25 May 2025
BBK strengthens commitment to sports development through strategic partnership with Bahrain Basketball Association
This website uses cookies to ensure you get the best experience and by clicking “I Accept” below, you consent to the use of cookies. Learn more