(MENAFN) The work on the Zallaq Harbor project in Bahrain is on track with several of the key development phases finished as per schedule.

Furthermore, the harbor has the capability to accommodate 112 boats, while the facility boasts 56 stores for sale of sailing equipment.

Additionally, the USD3.68mn project, which was given to Down Town, will cover block 733 in Nasfa and part of Block 743 in Sanad.

On the other hand, the work includes extending 6.1km of main connections and 2.9km sub-connections, constructing 622 lifting stations.