21 Mar 2016
(MENAFN) BP Oman proclaimed that the construction work of its Khazzan natural gas project is now 65 percent finished and the first gas is predicted in late 2017.
Moreover, the company’s work at Khazzan will make a huge contribution to Oman’s energy supply, increasing energy security and the country’s foundations.
In addition, BP Oman is a lead partner in the project with a 60 percent interest, whereas Oman Oil Company Exploration and Production holds 40 percent.
Many deals were signed with the Ministry of Oil and Gas to amend the Block 61 exploration and production sharing agreement, to enable other stage of development.
17 Nov 2024
BBK and Asia Jewellers announce exclusive offers to its customers at Jewellery Arabia 2024
12 Nov 2024
BBK partners with Durrat Al Bahrain to offer exclusive financing for Jawhart Al Marjan
05 Nov 2024
As part of its digital transformation journey, BBK adds Google Wallet to its range of digital wallets
This website uses cookies to ensure you get the best experience and by clicking “I Accept” below, you consent to the use of cookies. Learn more