FINANCIAL NEWS

Dubai Expo 2020 Dubai Park installation 80pct finished

21 Jun 2017

(MENAFN) Dubai Elect and Water Authority (Dewa) proclaimed that its 132-11kV substation being installed amid the Expo 2020 Dubai Park is 80 percent finished.

Moreover, the substation named Mobility with a capacity of 150 megavolt amperes is one of the three main substations, being built by Dewa.

Additionally, the substations, which high-voltage 132kV cables increasing over 45km, are being enhanced at an estimated cost of USD114mn.

Meanwhile, Dewa is working on a project to extend main water transport networks, utilizing 600-and 1.200mm- diameter pipes.