Oman cement repairs grinding mill

12 Jun 2013

(MENAFN) Oman Cement Company shuts down a grinding mill after monitoring technical problem, reported Times of Oman.

The production capacity of the mill is 150 tones per hour.

The spare parts of the mill will be available within 14 weeks the technical expert said after conducted the inspection

It is worth noting that production will be lower by about 360,000 tonnes during the period of June to September of this year.