10 Jul 2017
(MENAFN) A Mitsui & Co Ltd-led consortium achieved progress in building two main natural gas-fired power projects in Oman, which will have a joined capacity of 3.219MW.
Moreover, the Ibri Independent Power Project will get power of 940MW from April 2018, with the whole 1.509MW generation projected from April 2019.
Meanwhile, Sohar 3 is scheduled to receive full capacity of 1.710MW from Jan 2019, while the cooling tower work is progressing at the Sohar project.
In addition, the Mitsui-led group has tight deadlines to finish these two projects as OPWP is aiming to generate power amid two years.
MENAFN1007201700450000ID1095611036
MENAFN1007201700450000ID1095611036
05 Aug 2024
With the support of BBK, BIBF and BJA hold a graduation ceremony for journalists completing the training program
09 Jun 2024
BBK Successfully Closes USD Benchmark Bond Offering at $500 Million, in Collaboration with a Consortium of Regional and International Banks.
This website uses cookies to ensure you get the best experience and by clicking “I Accept” below, you consent to the use of cookies. Learn more